Skip To ContentAbout the CityCity ServicesCity GovernmentVisit PasoBusiness DevelopmentVolunteer
City of Paso Robles
DepartmentsCity CouncilAdvisory BodiesPlanning Commission
Address
Capital Projects Engineering
1000 Spring Street
Paso Robles, CA 93446
Phone
(805) 237-3861
(805) 237-3904 FAX
Hours
Mon-Fri 8am to 5pm
E-mail
cipengineering@prcity.com
Engineering Division

CAPITAL IMPROVEMENT PROJECTS IN PROGRESS

Click on the links below to see pictures of each project update.

'Hot Spot' Street Repairs (DPW 13-10)

March 24, 2014
The hot spot repair locations have been re-striped, utility covers raised and is now complete.

March 11, 2014
Attached is a photo update of more "hot spot" areas completed at:

  • Charolais at Ladera
  • Charolais at Arbolada
  • Niblick (westbound lane just east of Melody)
    Golden Hill at Via Colina

February 21, 2014
Completion of "hot spots" pavement repair work at:

  • Pacific at Merry Hill
  • 4th Street at Pine
  • 12th Street at Vine
  • Vine at 12th Street
  • 8th Street between Spring and Park

Long-Term Parking - Pine Street (DPW 13-06)

October 18, 2013
The City has removed the old mini-storage at Pine (across form Park) to make way for the construction of a Park-n-Ride lot. Funding of the project is coming from Transit Funds.

Oak Park Sewer Construction (DPW 12-11)

May 22-23, 2013
The contractor has completed boring under the railroad tracks. He is now setting up the sewer by-pass system and installing new sewerlines that will connect to the pipes that were pulled under the railroad tracks.

Rambouillet Road Repair (DPW 12-10)

Photo Summary of Work Completed
CalPortland, Pavement Engineering Inc, Penfield and Smith were the project team. They did a great job!

Turtle Creek Path Upgrade (DPW 11-07b)

April 9, 2014
The CDBG funded Turtle Creek path improvement project is now complete.

March 24, 2014
The City is removing the dilapidated and worn-out asphalt path known as "Turtle Creek Path" located along Brookhill between Westfield and Airport Road. The path will be replaced with concrete. In addition handicap ramps adjacent to and leading to the path are also being upgraded to meet ADA requirements. The project is paid for using CDBG Funds administered by Community Development.

Merry Hill Water Tank Rehabilitation (DPW 11-03)

April 10, 2013
Work should be completed in a couple of weeks and Water Division staff are planning on filling it up with water by early June - in time for this summer’s water service demands.

21st Street Improvement Project (DPW 10-17A)

March 17, 2014
Before and After Complete Green Street Upgrade. Before photos taken December 2009 and February 2011. After photos March 2014.

Photo Summary of Work Completed
The 21st Street Project summary of photos from May - November 2013.

Additional Resources

15th Street Sewer Upgrades (DPW 10-04A)

Photo Summary of Work Completed
The Sewer/Water Upgrade project along Riverside and 15th Street is complete.

46 East/13th Street Bridge (DPW 06-01A)

April 2, 2014
Papich is continuing with drainage work, signal pole, grading and preparing old southbound Hwy 101 ramp at 24th street by Denny’s. This week they are continuing with final grading on the old ramp to get it to the point of placing base and final asphalt in the next couple of weeks.

March 17, 2014
Papich is now working at the 24th Street area of Highway 101/46East, excavating the old ramp in order to re-construct it per Caltrans requirements.  A new storm drain is also under construction under the Hwy 101 bridge.

January 30, 2014
As the attached photos show, final asphalt paving was completed at 13th Street Bridge deck. Work performed the nights of January 29 and 30, 2014.

January 15, 2014
Papich will be removing the K-rails currently at the bridge. This area will then be available for traffic to use for northbound right turn lane at Riverside.

October 18, 2013
The area east of the Bridge (in front of Palla Bldg) has been graded/base placed and compacted and ready for concrete curb, gutter and sidewalks for quite some time.

October 14, 2013
Photo updates of the work at the 13th Street Bridge, north side.  The work progress may not be as noticeable because they are now installing storm drain pipes.

Show/Hide More DPW 06-01A Project Updates

September 24, 2013
Work is progressing on the north side of the bridge with the installation of a new bridge barrier and new signal poles. Fencing along Riverside is also being removed and replaced. Work is on schedule for the WHOLE project (bridge, new on/off ramps at 17th Street, dual southbound ramps from Hwy 46, improvements along Riverside) to be completed, Summer 2014.

September 10, 2013
Retaining walls under bridge are complete and backfilled (9/5/13).
Utility boxes and conduits in place under future sidewalk (9/6/13).
Sidewalk rebar and bridge barrier rebar at 13th St. Bridge are in place (9/10/13).
East of bridge catwalk in place – workers will use
as they construct the bridge barrier (9/10/13).

August 16, 2013
Existing sidewalk, curb, gutter east of 13th Street (north side) removed.
Forms on retaining wall below 13th Street Bridge have been removed.
Forms and concrete placed on abutment wall east side of bridge.
Contractor performing backfill and compaction for retaining wall below 13th Street Bridge.

July 30, 2013
Demo of bridge abutment at east end of bridge.
Retaining wall at west end of bridge is formed.
Demo of bridge abutment at east end of bridge.

July 18-25, 2013
The old barrier and sidewalk of the bridge has been removed. The contractor is now working on the large retaining wall that is needed to support the future widened curb return at 13th and Riverside.

June 28, 2013
Papich is proceeding with the next phase of work at the 13th St Bridge/17th off/on ramp/46east on-ramp project. Details are listed in the attached PDF.
They will also be buttoning up the area by July 15th and work will be on pause until after the Mid-State Fair.

June 10, 2013
The plywood screens on top of the K-rails have been removed.  This is in preparation of the work for June 11th at 8PM.

The bridge will be closed to traffic (between Riverside and Paso Robles Street) at 8PM Tuesday night and will open again by 6AM on Wednesday, June 12th. The K rails currently on the south side will be moved to the north side so that work may begin on the north side of the bridge. Current lane configurations on the bridge will remain the same but will be re-striped to shift to the south. 

May 16, 2013
Installed the panels for the railings on the barrier over Highway 101.
Re-installing catwalk to the north side.
Moving the project to the north and opening up the south side of the bridge.

Feb - March 2013
Sidewalk, curb and gutter east of the bridge is completed.
New signal pole on southwest corner Paso Robles/13th.
All underground utilities east of the Bridge has been relocated.
Fencing behind the Event Center property is 80% complete.

Jan-Feb 2013
Work at the bridge is about 70% complete.
Papich also has a crew performing the grading of the new off/on ramps at 17th and Riverside.
Work behind the Event Center is also on-going.
South side of the bridge is slated for completion by late Spring/early summer and then will re-open.

December 2012
Installation of temporary barrier and walkway.
Compaction and backfill of southwest abutment; Southeast wall complete.
Sidewalk grading; storm drains installed.

November 2012
Rebar installed for new sidewalks and concrete barriers.
Backfill and compaction behind southwest abutment wall.
Southeast abutment formed and concrete installed and curing.

October 2012
In addition to the work at the bridge, contractors have been working at the Paso Robles Event Center
New signal installed at 24th Street.

August 14, 2012
ATT is continuing to work in installing new conduits.
Papich is continuing with the wall as shown in the photos.

July 26, 2012
Photos show rebar being installed for the retaining wall that is needed to support the widened curb return that will be constructed at the southeast corner 13th and Riverside. Earlier this week, the rebar was completed and concrete was placed. The concrete is now curing before they take out the forms and then begin structural backfill for the retaining wall.

July 18, 2012
Removed the old bridge barrier and portions of the sidewalk.
ATT has placed new conduits in the sidewalk.
Installed storm drain lines along Hwy 101.
Installed shoring plates below the 13th street bridge at Riverside.

HWY 101/46 West Interchange Modification Project

Project information

 

Top


You are here:   Home  »  Government  »   Departments  »  Public Works  »  Capital Projects In Progress