Skip To ContentAbout the CityCity ServicesCity GovernmentVisit PasoBusiness DevelopmentVolunteer
City of Paso Robles
DepartmentsCity CouncilAdvisory BodiesPlanning Commission
Address
Capital Projects Engineering
1000 Spring Street
Paso Robles, CA 93446
Phone
(805) 237-3861
(805) 237-3904 FAX
Hours
Mon-Fri 8am to 5pm
E-mail
cipengineering@prcity.com
Engineering Division

CAPITAL IMPROVEMENT PROJECTS IN PROGRESS

Click on the links below to see pictures of each project update.
See a list of Completed Projects here.

24th Street Bridge Over the Railroad Tracks (DPW 16-01)

The existing bridge over the UPPR tracks was constructed in 1959. The bridge was constructed with 2 lanes of traffic, and a narrow sidewalk on the south side with no bike lanes. It has been a long-time priority by the City Council to improve this bridge.

The City has a Highway Bridge Program (HBP) Grant, in the amount of $723,714, for final design. In September 2016, the City engaged the services of AECOM to perform the work (after a thorough Federal-Aid procurement process). A Notice to Proceed was issued in October 2016.

Current work is to gather field data to begin the design work. We need to do some borings in the UPRR right-of-way, to get soils data and perform construction surveying. We are in the process of procuring an encroachment permit from UPRR, which is a 6-8 month process.

Final design is anticipated to be completed within 18-24 months. The City will then apply to Caltrans for a Grant to construct the project.

Annual Refreshment Pavement Striping and Markings (DPW 16-07)

Refresh pavement striping and markings at various locations:

  • Creston Road: Beachwood to Meadowlark
  • Creston Road: Cedarwood to Niblick
  • Golden Hill Road: Creston to Union
  • 13th / S. River Road: Arrows and turn pockets
  • Tower Road: Airport to Jardine
  • Fontana: Sherwood to Linne
  • Downtown Area: Stop and Limit Lines
  • Angled parking lines at various locations.

Work to begin: June 2017
Completion: October 2017

Creston Road Hot Spot Repairs and At Various Locations (DPW 16-10)

The project will dig out and replace with new paving, the drive lane sections of Creston Road, Capitol Hill to Rolling Hills. In addition, other areas that have localized failures will also be dugout and replaced with new paving:

  • Niblick by Paso Robles High School
  • 24th Street, westbound at Park
  • 24th Street, westbound at Vine
  • 13th Street, eastbound at Pine
  • Near 1828 Saint Andrews Circle
  • Prospect Avenue, northbound Union to Mesa
  • Tower Road: Airport to Jardine.

Work to begin: June 2017
Completion: October 2017

Sherwood Sewer Replacement (DPW 16-21)

Due to aging infrastructure and increase frequency of high maintenance activity to keep the sewer system of Tract 67 (circa 1952), and Tract 172 (circa 1959) clear and functional, the City has decided to proceed with a sewer replacement project to restore integrity to the system and to significantly reduce the potential for sewer system overflows (SSOs), public health concerns and costly fines. The scope of the project generally consists of:

  • Replacement of approximately 5,000 linear feet of 6 inch diameter vitrified clay (VCP) gravity sewer pipe using trenchless construction methods, within the backyard easements and alleyways of the 124 lots fronting the following streets: Santa Fe Ave., Santa Cruz Ave., Santa Ysabel Ave., Santa Ynez Ave., San Carlos Dr., San Augustine Dr., San Fernando Dr., Via Ramona Dr., and San Rafael Dr.
  • Restoration of approximately 124 lateral connections to the new sewer lines.
  • Repair/replacement of approximately 20 sewer manholes and cleanouts.

13th Street Pedestrian Improvements from Park to Pine Street (DPW 16-23)

The City of Paso Robles has received a Grant to initiate the design work to improve and enhance pedestrian safety and amenities along the corridor.  The project is in the Preliminary Design stage.  Once the project is accepted for final design, then funding for the project will be allocated and will then move into the construction phase.

Spring Street - 10th to 16th (DPW 12-12F-3)

Planned Construction:

  • Conduits for future fiber optics and signal synchronization from 10th to 16th.
  • Upgrade sewer main across 14th Street.
  • Repair miscellaneous water valves, water services and fire hydrant repairs.
  • Fill in gaps of street trees (approximately 6-8).
  • Replace traffic loops with video camera detection at 12th and 13th Street traffic signals.
  • Improve drainage at 13th and 14th Street intersection
  • Remove and replace deteriorated asphalt (full width), from 10th to 16th.

Work began: April 2017
Completion: Late summer 2017

April 24, 2017 Update

  • Upgrade of old sewer pipe across 14th at Spring Street is complete
  • Miscellaneous upgrade and repairs of old water services, valves, fire hydrant lines are complete
  • Work has moved to the replacement of old water pipes across 13th Street

NOTE: All work is being performed at night because water services have to be shut down and to alleviate impact to traffic

Spring Street - 24th to 36th (DPW 12-12F-4)

The project is in the design stage, and will feature the following items:

  • Upgrade old and undersized water mains to meet fire flow demand.
  • Upgrade old sewer mains and replace old manhole covers.
  • Install conduit for future fiber optics line.
  • Repair damaged curbs, gutters, and sidewalks.
  • Address drainage deficiencies.
  • Remove and replace deteriorated asphalt (full width) from 24th to 36th

Construction schedule: Summer 2018

Creston Road Planning Grant (DPW 12-12H-1)

Please visit www.prcity.com/CrestonRoad for more information.

Sherwood Repairs - Creston to Linne (DPW 12-12I)

May 1, 2017
Final design for the repair of Sherwood - Creston to Linne has began so that it can be in construction by 2018 per the adopted list of streets schedule using Supplemental Sales Tax. Last week, soils engineers were on-site to perform drilling of the existing roadway (see attached photos). The data from the borings will be used to establish the final street structure that will be needed for the road repairs. A few weeks ago, construction surveyors were also on-site to gather field data survey to be used for the final design as well.

Project will feature the following items:

  • Install a new traffic signal at Commerce.
  • Complete the missing curb, gutter, and sidewalk at the corner across from Food-4-Less.
  • Upgrade the old sewer pipes between Commerce and Linne.
  • Improve and resurface deteriorated asphalt.
  • Install additional street trees along the south side.
  • Install a landscaped raised median.
  • Install decorative streetlights.
  • Stripe and paint the bike lanes.

Construction schedule: Summer 2018

Vine Street - 32nd to Caballo (DPW 12-12J-1)

This is the dirt area behind the Georgia Brown School. The project is in the design stage, and has the following features:

  • Lowering of a shallow existing water main.
  • Grade and pave the dirt area with new asphalt.
  • Upgrade the curb ramps at 32nd and at Arlene.

Construction schedule: Summer 2018

May 5, 2017
The design work has begun with the field work to drill for soils data and perform infiltration test.

Top


You are here: Home Government Departments Public Works Capital Projects In Progress