TREATMENT PLANT UPGRADE PROJECT

Status Updates (DPW 08-14)

Total Project Cost: $46,200,000 in January 2014 dollars
Cost Incurred to Date: $4,900,000

Construction Activities

✓ Issued Notice to Proceed to W.M. Lyles on April 1, 2013
— Substantial Completion of Operations Building in Oct. 2014
— Substantial Completion of Liquid Process Facilities in Feb. 2015
— Substantial Completion of Solids Process Facilities in April 2015
— Substantial Completion of the Project and Phase II Facilities in Oct. 2015

Bidding and Pre-Construction Activities

✓ Pre-qualified contractors
✓ Advertised for bids in December 2012
✓ Opened bids in January 2013
Awarded contract to W.M. Lyles in February 2013

March 2013
Secured Low Interest State Loan

February 2012
CEQA/Permitting completed

April 2011
Planning and Design completed

Current Treatment Process

For more information on the current treatment process, use the following links.

Treatment Process

Physical Treatment  |  Primary Treatment  | Trickling Filters

Secondary Clarifiers  |  Bio Solids  |  Disinfection

Polishing Ponds  |  Laboratory

 