Following the closure of the bid submittal period, bids will be publicly opened and read for performing work as follows: Furnishing all labor, materials, equipment, and performing all work necessary and incidental to the construction of the project known as Annual Pavement Striping and Markers Refreshment, DPW Project No. 22-16, according to drawings and specifications prepared by the City of El Paso de Robles and according to the Contract Documents. The work shall include but is not limited to, removal of existing pavement lines and makers, preparation of surface to receive new pavement lines and markers, all as shown on the plans and/or as specified herein.
Project is to be completed within Thirty (30) WORKING days from the date specified in the Notice to Proceed. The Contractor shall pay to the City of El Paso de Robles the sum of Five Hundred Dollars ($500.00), for each and every calendar day’s delay in finishing the work in excess of the calendar day completion time.
WORK HOURS SHLL BE SUNDAY TO THURSDAY, 8:00 P.M. TO 5:00 A.M.